Ganga Expressway Complete Guide

Route: Meerut (Bijauli) to Prayagraj (Judapur Dandu) - 594 km
System: 6-lane access-controlled expressway (expandable to 8)
Status: Under construction - 84% complete (June 2025)
Expected Opening: Late 2025 (before Kumbh Mela)
Special Feature: 3.5 km emergency airstrip for IAF operations
Total Cost: ₹37,350 crores

When Will Ganga Expressway Open? 2025 Update

The Ganga Expressway is expected to open by late 2025, with construction currently 84% complete as of June 2025. UPEIDA is fast-tracking completion to have it operational before the Kumbh Mela in Prayagraj.

Key Reality: This will be UP's longest expressway at 594 km, connecting western UP (Meerut) with eastern UP (Prayagraj) and reducing travel time from current 12+ hours to just 8 hours.

2025 Update: Construction includes a unique 3.5 km emergency airstrip for Indian Air Force operations, successfully tested with Su-30MKI and other aircraft in May 2025.

Expected Toll Rates: FY 2025-26

UPEIDA has pre-fixed toll rates for Ganga Expressway aligned with the Wholesale Price Index (WPI) for FY 2025-26.

Projected Toll Rates (2025-26)

Vehicle Category Rate per KM Full Journey (594 km) Example Routes
Cars/Jeeps/Vans ₹2.55/km ₹1,515 Meerut to Prayagraj full route
Light Commercial Vehicles ₹4.25/km ₹2,525 Hapur to Hardoi section
Trucks (Standard) ₹8.15/km ₹4,841 Commercial freight routes
Oversized Trucks ₹16.05/km ₹9,534 Heavy cargo transportation

Major Section Costs (Projected)

Route Section Distance Car Cost Key Cities Connected
Meerut to Bulandshahr 85 km ₹217 Industrial corridor
Bulandshahr to Shahjahanpur 200 km ₹510 Airstrip location
Shahjahanpur to Hardoi 150 km ₹383 Central UP connection
Hardoi to Prayagraj 159 km ₹405 Kumbh Mela destination

Construction Progress & Route Details

Current Construction Status (June 2025)

Construction Component Progress Completed Status Key Milestones
Earthwork 99% Nearly Complete Base foundation ready
Granular Sub Base (GSB) 95% Advanced Stage Road layer construction
Wet Mix Macadam (WMM) 94% Advanced Stage Road strengthening layer
Dense Bituminous Macadam (DBM) 92% Advanced Stage Surface preparation
Structures (Bridges/Flyovers) 1,476/1,500 98% Complete Major Ganga bridge finished
Overall Progress 84% Final Phase Toll plaza setup remaining

Districts Connected (West to East)

  • Meerut: Starting point at Bijauli village, industrial hub
  • Hapur: Connection to Delhi-Meerut corridor
  • Bulandshahr: Major agricultural and industrial center
  • Amroha: Historic city with commercial importance
  • Sambhal: Traditional handicrafts center
  • Badaun: Agricultural trading hub
  • Shahjahanpur: Location of 3.5 km IAF emergency airstrip
  • Hardoi: Central UP connectivity point
  • Unnao: Industrial development zone
  • Rae Bareli: Political and administrative center
  • Pratapgarh: Historical significance, tourism potential
  • Prayagraj: Ending point at Judapur Dandu, Kumbh Mela venue

Special Features & Infrastructure

Emergency Landing Facility (IAF Airstrip)

A unique 3.5 km emergency airstrip has been constructed near Shahjahanpur for Indian Air Force operations. Successfully tested in May 2025 with multiple aircraft including Su-30MKI, Mirage 2000, MiG-29, Jaguar fighters, C-130J transport aircraft, and Mi-17 helicopters.

Major Infrastructure Components

  • 12-lane Ganga Bridge: 960-meter bridge with 16 pillars connecting both banks
  • Toll Plazas: 2 main toll plazas at Meerut and Prayagraj + 12 ramp toll plazas
  • Service Roads: 3.75m service roads for local village traffic
  • Rest Areas: 9 amenity complexes with food courts and facilities
  • Flyovers & Underpasses: 8 road over bridges, 8 flyovers, 26+ underpasses
  • Industrial Corridors: Planned along the route for economic development

Travel Benefits & Connectivity

Dramatic Time Savings

  • Meerut to Prayagraj: 12+ hours → 8 hours (33% time saving)
  • Delhi to Prayagraj: 10 hours → 7 hours (via Delhi-Meerut + Ganga)
  • Maximum Speed: 120 km/h for cars, enabling faster travel
  • Fuel Efficiency: 30-40% fuel savings due to smooth traffic flow

Economic & Tourism Impact

  • Kumbh Mela Access: Enhanced connectivity for 2025 Kumbh in Prayagraj
  • Industrial Development: Planned industrial corridors along the route
  • Agricultural Markets: Better access for farmers to urban markets
  • Tourism Boost: Improved access to Ganges river heritage sites
  • Real Estate Growth: Property development along the corridor

Payment & Technology Features

Toll Payment Methods (Expected)

  • FASTag Mandatory: Electronic toll collection for all vehicles
  • Digital Payments: UPI, credit/debit cards at toll plazas
  • Cash Backup: Limited cash lanes for emergency use
  • Mobile Integration: Smartphone apps for toll management

Safety & Monitoring Systems

  • CCTV Surveillance: 24/7 monitoring along entire route
  • Emergency Services: Patrol vehicles and ambulance services
  • Weather Monitoring: Advanced systems for monsoon and fog alerts
  • Speed Detection: Automated speed enforcement cameras

Frequently Asked Questions

When will Ganga Expressway be fully operational?

Expected by late 2025, with UPEIDA targeting completion before the Kumbh Mela. Current progress is 84% complete as of June 2025, with final toll plaza setup and signage work remaining.

Will two-wheelers be allowed?

No, like all UP expressways, two-wheelers and three-wheelers will be prohibited for safety reasons. Only four-wheelers and above will be permitted.

How much will it cost to travel the full route?

For cars, approximately ₹1,515 for the full 594 km journey from Meerut to Prayagraj, based on the pre-fixed rate of ₹2.55 per kilometer for FY 2025-26.

What makes this expressway special?

It will be UP's longest expressway, features a 3.5 km IAF emergency airstrip, connects 12 major districts, and includes a massive 12-lane bridge over the Ganga river. It's designed to handle speeds up to 120 km/h.

Useful Links & Resources

Related Information:

Official Contacts:

  • UPEIDA Helpline: 14449 (toll-free, 24/7)
  • UPEIDA Website: upeida.up.gov.in
  • Project Enquiries: Available through official channels

Found outdated construction status or toll information? Join us to keep expressway information current.